Wescan completed the Mechanical Installation for the Five storey Level 2 and 3 virology labs additions including the supply and installation of sophisticated HVAC systems, specialized sanitary systems, clinical autoclaves, and specialty fume hoods.

SCOPE OF WORK
  • High Pressure Steam system for Bio Hazard Rotoclave.
  • Medium Pressure Steam system for Autoclave.
  • Low Pressure Steam for Building Heating using a steam to glycol heat exchanger.
  • Low Pressure Steam for Building Humidification.
  • 1 AHU for Level 3 heating and air distribution.
  • 1 AHU for Level 2 heating and Air Distribution.
  • Both AHU’s used heat reclaim coils off building exhaust.
  • Bio Hazardous sanitary drainage.

download line card

Project Details

Owner: Public Health Agency of Canada
Type of Service: Mechanical
Sector: Institutional
Completed: May 2012
Value: $3,500,000
Delivery Method

Design, Bid, Build

Engineer

Smith Carter
Larry Wiens

Superintendent

Rob Beaulieu

Project Manager

Shawn Henry

Contractor

Bird Construction