Outlet Collection

Outlet Collection Winnipeg is a fully enclosed shopping centre development with a total retail floor area of 570,000 square feet.  It was a very challenging project, with over 1000 modifications due to constant tenant and leasing changes during construction. Wescan, PCL and the project team were able to work together to manage all of the revisions and complete construction on schedule.

SCOPE OF WORK
  • HVAC System which included 238 RTU’s, 10 MUA, Natural Gas Piping, Exhaust Fans, and Ductwork
  • Sanitary & Storm Sewer System
  • Domestic Water Systems
  • Building Automation System

download line card

Project Details

Owner: Ivanhoe Cambridge
Type of Service: Mechanical
Sector: Commercial
Completed: May 2017
Value: $8,770,000
Delivery Method

Bid Spec

Project Manager

Shawn Henry

Superintendent

Niels Kaczorowski

Engineer

Stantec Engineering

Contractor

PCL Constructors Canada